NTC installation procedure
Overall summary:
We need to remove the MVD from its position around the beam pipe, attach the
NTC to it, and reinstall the combined detectors. Due to space limitations, only
two people can effectively work in the central region at one time. A third
person is needed to wait at the bottom of the stairs to find tools, papers,
etc. In general, the time to install the T0 counter would have to be
added to the time to install this detector.
The time estimates below add up to 38.75 hours. This allows no little
contingency for problems (space, plumbing, electronics, etc). A sensible
estimate is to approximately double this time -- 2 days plus one shift. We would
like to start one morning, which should be a Monday, Tuesday, or Wednesday, and
end at the end of the day shift 56 hours later.
Most significant safety issue: Possible damage to Be beam pipe.
Solution: As per the PHENIX MVD installation procedures documented in
PHENIX Procedure Number PP-2.5.5.4-15, whenever possible, the beam pipe will be
protected by several inches of foam padding. Beam pipe vacuum should be isolated
during the installation. In addition, as much of the work as possible will take
place out of reach of the beam pipe (on a platform approximately 2.4 meters
below the beam line).
1 - Retract East and West Arms, Install ladder on West Side
of IR. |
Time estimate: 1 hour.
Items
needed: a ladder
Required assistance from PHENIX: retract the East and West
carriages.
2 - Retract He bag, cut away strings.
|
Time estimate: 1 hour
Items needed: not
sure
Required assistance from PHENIX: Retracting the He bag
3 - Install the MVD installation fixture on the lift table
|
Time estimate: 1 hour.
Items needed:
hex key (i.e. Allen wrench), medium sized flat head screwdriver, the parts of
the installation fixture.
Required assistance from PHENIX: none
4 - Remove the air cooling "pipes" from the ends of the air
cooling ducts on the MVD |
time estimate: 15
minutes
Items needed: a knive, something to cut cable ties
Required
assistance from PHENIX: none
5 - Lift table up and "capture" MVD
|
time estimate: 2 hours
Items needed:
allen wrenches for horizontal adjustment of installation fixture and for the
pieces which "capture" the MVD hinges, medium-sized flat screwdriver for pieces
which hold the MVD in the "open" position, large flat-had screw driver to push
in spring-loaded fixtures which capture the MVD on the nosecones, a long
entension cord to plug in the lift table.
Required assistance from PHENIX:
none
6 - Move MVD down by about 50 cm and uncable. Put foam
protection around the beam pipe. |
time
estimate: 1 hour
Items needed: something to cut cable ties
Required
assistance from PHENIX: none
7 - Replace copper water cooling lines w/flexible tubing
|
time estimate: 2 hour
Items needed:
tubing, wrench, RTV, patience w/water leaks
Required assistance from PHENIX:
none
8 - Attach extension cables and organize
|
time estimate: 2 hour
Items needed:
duct tape, cable ties
Required assistance from PHENIX: none
time
estimate: 2 hours
Items needed: allen wrench, screw driver, the NTCs
Required assistance from PHENIX: none
10 - Lift MVD+NTCs to installed position and attach to
nosecones |
time estimate: 6 hours
Items
needed: a flat head screw-driver, allen wrenches, a piece of aluminum
approximately 50x5x0.3 cm to push in springs, cable ties
Caveats: if needed,
the MVD low voltage cables may be modified to increase the space available for
the NTC counters. This modification has been approved by the safety committee
and would add about 2 hours to the time estimate quoted above.
Required
assistance from PHENIX: none
11 - Mount PMTs to nosecone
|
time estimate: 1 hour
items needed:
allen wrenches ?
Required assistance from PHENIX: none
12 - Tap into BBC compressed air line for venting NTC PMTs
|
time estimate: 3 hours
items needed:
not sure ?
Required assistance from PHENIX: gas person (Carter?)
time
estimate: 1 hour
items needed: not sure ?
Required assistance from
PHENIX: none
14 - Connect HV and signal cables
|
time estimate: 3/4 hour
items needed:
the cables, + ?
Required assistance from PHENIX: none
15 - Reattach MVD cables to extensions and reconnect
air-cooling ducts |
time estimate: 2 hours
items needed: duct tape, tube of RTV, cable ties, paper towels
Required
assistance from PHENIX: none
16 - Testing of electronics, readout, cabling, plumbing,
air-cooling |
time estimate: 2 hours
items needed: paper towels
Required assistance from PHENIX: none
17 - Repair of problems noted in previous step
|
time estimate: 4 hours
items needed:
good luck
Required assistance from PHENIX: none
18 - Cleanup, including removing installation fixture
|
time estimate: 1 hour
items needed:
trash bag
Required assistance from PHENIX: May need someone to survey the
trash (cable ties, etc.) for radioactivity
19 - Reinstall Helium bag
|
time estimate: 3 hours
items needed:
Helium bag, string, + ?
Required assistance from PHENIX: Someone to install
it
20 - Move East and West carriages back in
|
time estimate: 1 hour
items needed: not
sure
Required assistance from PHENIX: moving the carriages
21 - Sweep area and close up
|
time estimate: 2 hours
items needed:
not sure
Required assistance from PHENIX: CA people for sweep and closeup
Contact person for MVD Installation matters: John Sullivan
(sullivan@lanl.gov)
Contact people for NTC Installation matters:
Brendan Fox (deni@bnl.gov), Abhay Deshpande (abhay@bnl.gov)
updated 08-May-2001